At the Ecogreen Energy facility, epoxy chemical anchors were installed in the existing columns prior to the installation of the steel cantilever structure. Subsequently, the gusset plates, to which the main load-bearing beams would be connected, were welded to the existing factory columns.

The work was completed with the installation of the columns, main load-bearing beams, and secondary beams.

Proje Türü
Çelik Yapı Sistemleri
Konum
Denizli, Kaklık
Kapasite
25 mt Yükseklik
Metraj
12 tn.
Yapım Yılı
2026
İşveren
Uma Çelik Yapı